maxIT Success Story
In Less Than
12 Months...
 
Stanly Regional Medical Center Implemented an Electronic Health Record (EHR), an Enterprise Revenue Cycle Solution and Achieved Meaningful Use Compliance
 
 
 
Stanly Regional Medical Center
Stanly Success Story
Download
Client Profile/Background
Stanly Regional Medical Center is a regional medical center located in Albemarle, NC, approximately 42 miles from the financial hub of Charlotte. Stanly is part of Carolinas Health Care System, one of the largest health care systems in North Carolina, and the market leader in Charlotte. With a staff of health care professionals using the latest medical treatments and technology, Stanly Regional Medical Center offers advancements in cancer treatment, imaging, rehabilitation, women's services and more.
 
Rapid Implementation Approach
A decision was made for Stanly, the EHR vendor, and maxIT to utilize a rapid deployment and transformation framework in order to achieve their implementation goals.
This implementation approach integrated deliverables focused on readiness, workflow, adoption, and technology infrastructure with industry leading project management protocols for on-time, on-budget execution.
 
Close Collaboration
Cross-Functional Experienced Team
Stanly's Project Team, the EHR vendor, and the maxITTeam collaborated throughout the implementation process to achieve the following:
Define realistic project timelines and budgets;
Develop a clear adoption roadmap and risk mitigation strategy;
Establish the process for Team leaders to make decisions about the accelerated build process
Develop testing and training plans and processes utilizing strong subject matter experts to accomplish these important activities
Establish Steering and Project Team committees to meet on a regular basis, which enabled critical and timely decisions
One of the most important reasons for success was the early involvement of the physician sponsors.
 
Contributing Success Factors
Phased Implementation
The team phased the implementation of order entry for compliance and scheduling purposes. They also decided to have a multi-phased approach to the go-live.
 
Go-Live when 80% of the Medication Orders are Run Through the System
Phase 1 focused on going live with the goal of 80%+ of the medication orders placed through the system. They went live with order sets which incorporated the bulk of their medication orders and activities. At the end of the first thirty days, Stanly estimated that between 80-90% of all physicians were using the HIS. This included physicians using CPOE, signing off on chart deficiencies, utilizing the medication reconciliation and verification processes, and much more. Stanly's plans for Phase 2 include going live with additional order sets specifically for Surgery. Phase 3 plans include order sets for OB/GYN and Pediatrics.
 
Strong Participation by Stanly Leadership
Stanly Regional Medical Center made remarkable progress in a single year in achieving Meaningful Use Stage 1 and CPOE. The timeline provided significant barriers to overcome. However, Stanly's strong leadership team, influential physician guidance, effective planning and communication processes, clear focus on their end goals, and collaborative partnership with maxIT allowed Stanly to achieve significant success in record time.
 